Exploration of a lean-BIM planning framework: A last planner system and BIM-based case study

Mauricio Toledo, Katherine Olivares, Vicente González

Research output: Chapter in Book/Report/Conference proceedingConference contributionpeer-review

19 Citations (Scopus)

Abstract

Current Lean Construction and Building Information Modelling (BIM) research has been focused largely on the theoretical aspects related to their integration and synergies. But little attention has been paid to the development of BIM-Lean practical methods to manage projects and provide evidence of the opportunities for performance enhancement. In this paper, we attempt to bridge this gap by proposing a Lean-BIM planning framework by integrating the Last Planner System and BIM. The development of the proof of concept of the BIM-Lean planning framework was undertaken by comparing two case studies: one using only LPS and the other using LPS and BIM. We followed construction activities related to rough work in two comparable building projects as part of the field office staff. We gathered project data and analysed and compared planning procedures in both projects. Data collected included: Weekly and lookahead planning meetings analyses; design requests for information (RFI); and LPS metrics. We then used flowcharts to document both planning processes and the improved planning proposal, and also, integrated the different planning levels. Results show that the coordinated use of LPS and BIM generates an increase in PPC, a decrease in reasons for non-compliance, a shortening of the meeting durations, and a decrease in the total number of design RFIs. The improved planning proposal combines LPS+BIM and facilitates the interaction of a larger and diverse number of project stakeholders around BIM manipulation in planning meetings. Project meetings become more effective and the communication of project planning improves as a result.

Original languageEnglish
Title of host publicationIGLC 2016 - 24th Annual Conference of the International Group for Lean Construction
PublisherNational Pingtung University of Science and Technology
Pages3-12
Number of pages10
Publication statusPublished - 2016
Event24th Annual Conference of the International Group for Lean Construction, IGLC 2016 - Boston, United States
Duration: 18 Jul 201624 Jul 2016

Other

Other24th Annual Conference of the International Group for Lean Construction, IGLC 2016
Country/TerritoryUnited States
CityBoston
Period18/07/1624/07/16

Keywords

  • Last planner system
  • Lean-BIM
  • RFI

ASJC Scopus subject areas

  • Building and Construction
  • Civil and Structural Engineering

Fingerprint

Dive into the research topics of 'Exploration of a lean-BIM planning framework: A last planner system and BIM-based case study'. Together they form a unique fingerprint.

Cite this